Project Server 2003 Query to Get Project Assignments as Timephased
SELECT dbo.MSP_WEB_ASSIGNMENTS.TASK_NAME AS [Task Name], dbo.MSP_WEB_PROJECTS.PROJ_NAME AS Project,
dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY.AssignmentTimeStart, dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY.AssignmentTimeFinish,
dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY.AssignmentTimeWork / 60000 AS [Work], dbo.MSP_WEB_RESOURCES.RES_NAME
FROM dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY INNER JOIN
dbo.MSP_WEB_ASSIGNMENTS ON dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY.AssignmentUniqueID = dbo.MSP_WEB_ASSIGNMENTS.ASSN_UID AND
dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY.WPROJ_ID = dbo.MSP_WEB_ASSIGNMENTS.WPROJ_ID INNER JOIN
dbo.MSP_WEB_PROJECTS ON dbo.MSP_VIEW_PROJ_ASSN_TP_BY_DAY.WPROJ_ID = dbo.MSP_WEB_PROJECTS.WPROJ_ID INNER JOIN
dbo.MSP_WEB_RESOURCES ON dbo.MSP_WEB_ASSIGNMENTS.WRES_ID = dbo.MSP_WEB_RESOURCES.WRES_ID
Note: Please do test this query on local development environment before testing in on production.
Jerry